[1]张瑞明,李示波.威布尔分布计算充填采矿地表变形[J].中国安全生产科学技术,2013,9(8):59-63.[doi:10.11731/j.issn.1673-193x.2013.08.011]
 ZHANG Rui ming,LI Shi bo.Application of Weibull distribution in calculating ground deformation due to backfill mining[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2013,9(8):59-63.[doi:10.11731/j.issn.1673-193x.2013.08.011]
点击复制

威布尔分布计算充填采矿地表变形
分享到:

《中国安全生产科学技术》[ISSN:1673-193X/CN:11-5335/TB]

卷:
9
期数:
2013年8期
页码:
59-63
栏目:
学术论著
出版日期:
2013-08-30

文章信息/Info

Title:
Application of Weibull distribution in calculating ground deformation due to backfill mining
文章编号:
20130811
作者:
张瑞明 1 李示波 2
(1.山西工程职业技术学院 管理工程系,山西太原030009; 2.河北联合大学 矿业工程学院,河北唐山063009)
Author(s):
ZHANG Ruiming1 LI Shibo2
(1. Management engineering department, Shanxi Engineering Vocational College, Taiyuan Shanxi 030009, China; 2. College of Mining Engineering, Hebei United University, Tangshan Hebei 063009, China)
关键词:
威布尔分布开采沉陷倾斜变形充填采矿
Keywords:
weibull distribution mining subsidence inclination deformation backfill mining
分类号:
X936
DOI:
10.11731/j.issn.1673-193x.2013.08.011
文献标志码:
A
摘要:
为了准确分析采矿引起的地表沉陷变形对地表高压供电线路的影响,采用威布尔(Weibull)分布法计算地表下沉与偏斜值的大小。威布尔分布法计算充填采矿地表变形能够将地表变形的多个参数用于计算,并且函数便于用MATLAB编程处理。通过冀东一个铁矿的计算实例说明,采用充填采矿法控制地表变形后高压供电线路能够安全运行,该计算方法能够满足工程计算需要。
Abstract:
Weibull distribution was been used to calculate the ground subsidence and inclination value, in order to analysis accurately the influence of ground subsidence caused by underground mining on high voltage electric power lines. Many parameters could be used to calculate ground deformation due to backfill mining when Weibull distribution method was used; and the function could be solved by MATLAB program. An example of analysis of iron mine in the east of Hebei was given, and the results showed that the effect of reducing ground subsidence was notable and the high power line was working normally. It was accurate enough to calculate ground deformation by using Weibull distribution.

参考文献/References:

[1] 梅松华,盛谦,李文秀. 地表及岩体移动研究进展[J]. 岩石力学与工程学报,2004,23(1):4535\|4538 MEI Songhua, SHENG Qian, LI Wenxiu. Research advances in surface and rockmass movement [J]. Chinese Journal of Rock Mechanics and Engineering, 2004, 23(1): 45354538
[2] 刘同有. 充填采矿技术与应用[M]. 北京:冶金工业出版社,2001
[3] 秦豫辉,田朝晖. 我国地下矿山开采技术综述及展望[J]. 采矿技术,2008,8(2):1\|3 QIN Yuhui, TIAN Chaohui. Review and prospect of mining technology of underground mining in China[J]. Mining Technology, 2008, 8(2): 13
[4] 常庆粮,周华强,秦剑云,等. 膏体充填材料配比的神经网络预测研究[J]. 采矿与安全工程学报,2009,26(1):1\|10 CHANG Qingliang, ZHOU Huaqiang, QING Jianyun, et al. Using artificial neural network model to determine the prescription of paste filling materials[J]. Journal of Mining & Safety Engineering, 2009, 26(1): 110
[5] 王运敏. “十五”金属矿山采矿技术进步与“十一五”发展方向[J]. 金属矿山,2007,378(12):1\|10 WANG Yunmin. Progress in mining technology for metal mines in "TenthFive Year Plan" period and its development orientation in "EleventhFive Year Plan" period[J]. Metal Mine, 2007, 378(12): 110
[6] 李文秀,赵胜涛,梁旭黎,等. 宜昌磷矿地下开采岩体移动分析[J]. 岩土力学,2006,27(1):137\|140 LI Wenxiu, ZHAO Shengtao, LIANG Xuli, et al. Analysis of rock mass displacements due to underground mining of phosphorus oredeposit in Yichang mining areas[J]. Rock and Soil Mechanics, 2006, 27(1): 137140
[7] 颜荣贵. 地基开采沉陷及其地表建筑[M]. 北京:冶金工业出版社,1995
[8] 邹友峰,邓喀中,马伟民. 开采沉陷控制工程[M]. 徐州:中国矿业大学出版社, 2003
[9] 刘文生. 覆岩离层注浆充填保护地面高压线路试验研究[J]. 煤炭学报,2001,26(3):236\|239 LIU Wensheng. Experimental study on protecting high voltage electric power lines by grouting separated strata zone in overburden[J]. Journal of China Coal Society, 2001, 26(3): 236239
[10] 殷作如,邹友峰,邓智毅,等. 开滦矿区岩层与地表移动规律及参数[M]. 北京:科学出版社,2010
[11] 郭振华,周华强,武龙飞,等. 膏体充填工作面顶板及地表沉陷过程数值模拟[J]. 采矿与安全工程学报,2008,25(2):172\|175 GUO Zhenhua, ZHOU Huaqiang, WU Longfei, et al. Numerical simulation for roof and surface subsidence process caused by paste filling [J]. Journal of Mining & Safety Engineering . 2008, 25(2): 172175

相似文献/References:

[1]韩光胜,程健维,易光旺.国外矿山开采沉陷预计技术研究及应用概述[J].中国安全生产科学技术,2011,7(10):41.
 HAN Guang-sheng,CHENG Jian-wei,YI Guang-wang.The overview of research and application on foreign mining subsidence prediction[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2011,7(8):41.
[2]题正义,屈年华,时星.矿山开采沉陷可视化系统设计开发及岩移参数求取[J].中国安全生产科学技术,2015,11(1):97.[doi:10.11731/j.issn.1673-193x.2015.01.016]
 TI Zheng-yi,QU Nian-hua,SHI Xing.Design and development on visualization system of mine mining subsidence and calculation of rock movement parameters[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2015,11(8):97.[doi:10.11731/j.issn.1673-193x.2015.01.016]
[3]张程,马晓东,杨可明.结合遥感影像的矿山开采沉陷专题信息三维表达[J].中国安全生产科学技术,2016,12(7):87.[doi:10.11731/j.issn.1673-193x.2016.07.016]
 ZHANG Cheng,MA Xiaodong,YANG Keming.Three-dimensional expressing on thematic information of mining subsidence combined with remote sensing images[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2016,12(8):87.[doi:10.11731/j.issn.1673-193x.2016.07.016]
[4]高峰,肖蓉兰,高如高.金属矿山地表沉陷的可拓评价预警[J].中国安全生产科学技术,2016,12(12):53.[doi:10.11731/j.issn.1673-193x.2016.12.009]
 GAO Feng,XIAO Ronglan,GAO Rugao.Extension assessment and early-warning for surface subsidence of metal mine[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2016,12(8):53.[doi:10.11731/j.issn.1673-193x.2016.12.009]
[5]李敏睿,王海清,姚竣瀚,等.安全联锁设备SIL验证中的参数估计偏差分析*[J].中国安全生产科学技术,2021,17(6):24.[doi:10.11731/j.issn.1673-193x.2021.06.004]
 LI Minrui,WANG Haiqing,YAO Junhan,et al.Deviation analysis of parameter estimation for SIL verification of safety interlock equipment[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2021,17(8):24.[doi:10.11731/j.issn.1673-193x.2021.06.004]

备注/Memo

备注/Memo:
-
更新日期/Last Update: 2013-09-11