|本期目录/Table of Contents|

[1]陶铁军,池恩安,赵明生,等.露天铁矿分区爆破振动监测与安全分析[J].中国安全生产科学技术,2012,8(12):179-183.
 TAO Tie jun,CHI En an,ZHAO Ming sheng,et al.Monitoring and safety analysis of division blastinduced vibration for open pit iron mine[J].JOURNAL OF SAFETY SCIENCE AND TECHNOLOGY,2012,8(12):179-183.
点击复制

露天铁矿分区爆破振动监测与安全分析
分享到:

《中国安全生产科学技术》[ISSN:1673-193X/CN:11-5335/TB]

卷:
8
期数:
2012年12期
页码:
179-183
栏目:
出版日期:
2012-12-31

文章信息/Info

Title:
Monitoring and safety analysis of division blastinduced vibration for open pit iron mine
文章编号:
1673-193X(2012)-12-0179-05
作者:
陶铁军12池恩安2赵明生2张光权1汪旭光3
(1 北京科技大学 土木与环境工程学院,北京〓100083)(2 贵州新联爆破工程有限公司, 贵州 贵阳〓550002)(3 北京矿冶研究总院,北京〓100070)
Author(s):
TAO Tie jun 12 CHI En an 2 ZHAO Ming sheng 2 ZHANG Guang quan 1 WANG Xu guang 3
(1 School of Civil and Environmental Engineering, University of Science and Technology Beijing, Beijing 100083, China)(2 Guizhou Xinlian Blasting Engineering Limited Corp,Guiyang, Guiyang Guizhou 550002, China) (3 Beiing General Research Institute of Ming & Metallurgy, Beijing 100070, China)
关键词:
分区爆破振动监测安全分析干扰降振评判标准
Keywords:
division blasting vibration monitoring safety analysis waveform interference for vibration reduction judging standard
分类号:
X936
DOI:
-
文献标志码:
A
摘要:
对放马峪铁矿三个采矿场分区爆破的振动速度进行了监测,在剔除异常值后得到了106组三向振动的峰值速度,然后对三向振动速度分别进行回归分析。分析结果表明:放马峪铁矿采取的爆破分区方案是安全可行的,符合《爆破安全规程》(GB6722-2003)的规定;爆破振动的三相回归公式中K值较小、α值较大,说明了毫秒延时爆破能够加快地震波的能量耗散,从而起到干扰降振的作用;同一次爆破中,爆破振动速度的垂直向分量不一定总是最大,在评价爆破振动产生的破坏时,不应单一选取爆破振动速度的垂直分量作为评判标准,而应选择建构筑物所处位置振动速度分量中的最大值。
Abstract:
The vibration velocities induced by division blasting in three stopes of Fangmayu iron mine were monitored, totally, 106 seismic waves signal data were taken after getting rid of the exceptional value, then the data of three component of blasting velocity were used to make regression analysis respectively. The value of k and α of vertical component, longitude component and transverse component of PPV were all obtained. Based on these, the predictor formulas were established, which can be used to predict the vibration velocity generated by blasting. The analysis results showed that the value of actual monitoring data and predictor data both below the rule of “Blasting Safety Regulations” (GB67222003), so the “safety division blasting method” taken by Fangmayu Iron Mine is feasible and safety; the regression values of K are relatively small while the regression values of α are relatively big, which indicate that the millisecond delay blasting can accelerate the energy dissipation of seismic waves, inducing the effect of waveform interference for vibration reduction. The vertical component of blasting velocity is not always the biggest one, so the criterion is not always the vertical component of PPV but the maximum one when predicting whether the constructions will be destroyed by blasting vibration.

参考文献/References:

-

相似文献/References:

备注/Memo

备注/Memo:
-
更新日期/Last Update: 2012-12-31