[1]荆宏亮,李亮,李堂飞,等.考虑土体参数和锚杆承载力随机性的桩锚深基坑安全评价方法*[J].中国安全生产科学技术,2025,21(12):142-151.[doi:10.11731/j.issn.1673-193x.2025.12.018]
 JING Hongliang,LI Liang,LI Tangfei,et al.Safety evaluation method for pile-anchored deep foundation pit considering the randomness of soil parameters and anchor capacity[J].Journal of Safety Science and Technology,2025,21(12):142-151.[doi:10.11731/j.issn.1673-193x.2025.12.018]
点击复制

考虑土体参数和锚杆承载力随机性的桩锚深基坑安全评价方法*

《中国安全生产科学技术》[ISSN:1673-193X/CN:11-5335/TB]

卷:
21
期数:
2025年12期
页码:
142-151
栏目:
职业安全卫生管理与技术
出版日期:
2025-12-30

文章信息/Info

Title:
Safety evaluation method for pile-anchored deep foundation pit considering the randomness of soil parameters and anchor capacity
文章编号:
1673-193X(2025)-12-0142-10
作者:
荆宏亮李亮李堂飞胡俊
(1.青岛理工大学 土木工程学院,山东 青岛 266520;
2.青岛新华友建工集团股份有限公司,山东 青岛 266101;
3.海南大学 土木建筑工程学院,海南 海口 570228)
Author(s):
JING Hongliang LI Liang LI Tangfei HU Jun
(1.School of Civil Engineering,Qingdao University of Technology,Qingdao Shandong 266520,China;
2.Qingdao Xinhuayou Construction Engineering Group Co.,Ltd.,Qingdao Shandong 266101,China;
3.School of Civil and Architectural Engineering,Hainan University,Haikou Hainan 570228,China)
关键词:
桩锚深基坑安全评价随机性有限元熵值法可拓评价
Keywords:
pile-anchored deep excavation safety evaluation randomness finite element entropy methodextension evaluation
分类号:
X947
DOI:
10.11731/j.issn.1673-193x.2025.12.018
文献标志码:
A
摘要:
为更加合理地评价基坑安全性,将土体参数(土体刚度、黏聚力、内摩擦角)和锚杆轴向侧摩阻力视为服从对数正态分布的随机变量,基于Python语言编写程序调用PLAXIS 3D进行基坑开挖模拟,获取各施工步下基坑的安全评价指标值(地表沉降、坑底隆起、桩顶水平位移、桩顶沉降、桩(墙)体弯矩以及锚杆轴力)。利用熵值法确定各评价指标的权重,并基于可拓评价模型分析每组样本下基坑的安全等级。研究结果表明:传统评价方法仅能给出1个确定的安全等级,而本文方法在考虑土体及结构参数的随机性后,可结合不同安全等级的频次综合评价基坑的安全等级,并确定对基坑安全有显著影响的评价指标(地表沉降和桩顶水平位移);与传统方法相比,本文方法能够更合理、全面地评价基坑安全等级。研究结果可为桩锚深基坑安全评价提供参考。
Abstract:
In order to more rationally evaluate the safety of deep foundation pits,soil parameters (soil stiffness,cohesion and internal friction angle) and the axial side friction resistance of anchors are treated as lognormal random variables,and a Python-based program is developed to invoke PLAXIS 3D for excavation simulation so as to obtain,at each construction stage,the values of safety evaluation indices for the foundation pit (including surface settlement,base heave,pile-head horizontal displacement,pile-head settlement,bending moment of the pile or wall,and anchor axial force).The entropy weight method is used to determine the weight of each evaluation index,and an extension evaluation model is then employed to analyze the safety grade of the foundation pit for each sample.The results show that traditional evaluation methods can only provide a single deterministic safety grade,whereas the proposed method,after accounting for the randomness of soil and structural parameters,can comprehensively evaluate the safety grade of the foundation pit by combining the frequencies of different safety grades and can identify the evaluation indices that have a significant influence on pit safety (surface settlement and pile-head horizontal displacement).Compared with traditional methods,the proposed approach can evaluate the safety grade of foundation pits in a more reasonable and comprehensive manner.The findings can provide a reference for safety evaluation of pile-anchor deep foundation pits.

参考文献/References:

[1]PLUMB P.Safety factors and the probability distribution of soil strength[J].Canadian Geotechnical Journal,1970,7(3):225-242.
[2]WU T H,KRAFT L M.Safety analysis of soil profile[J].Journal of the Geotechnical Engineering Division,ASCE,1970,96(SM2):123-131.
[3]PAUL F,NEO B H,WEN D Z.Design and construction of earth retaining walls for deep excavation-a risk management process[J].The IES Journal Part A:Civil & Structure Engineering,2012,5(3):204-209.
[4]WEI D J,XU D S,ZHANG Y.A fuzzy evidential reasoning-based approach for risk assessment of deep foundation pit[J].Tunnelling and Underground Space Technology,2020,97:103232.
[5]魏新江,邓志秋,魏纲,等.可拓评价方法和熵值法相结合的基坑安全评价[J].岩土工程学报,2008,30(增刊1):672-676. WEI Xinjiang,DENG Zhiqiu,WEI Gang,et al.Safety evaluation of foundation pits by extension assessment method combined with entropy law[J].Chinese Journal of Geotechnical Engineering,2008,30(Supplement 1):672-676.
[6]陈绍清,熊思斯,何朝远,等.地铁深基坑坍塌事故安全风险分析[J].安全与环境学报,2020,20(1):52-58. CHEN Shaoqing,XIONG Sisi,HE Chaoyuan,et al.Safety risk analysis for the deep foundation pit collapse accidents in the subway construction system[J].Journal of Safety and Environment,2020,20(1):52-58.
[7]王伟,刘丹娜,彭第.基于熵值法的砂卵石地层深基坑开挖安全可拓评价[J].西南交通大学学报,2021,56(4):785-791,838. WANG Wei,LIU Danna,PENG Di.Extension evaluation on excavation safety of deep foundation pit in sandy cobble stratum based on entropy method[J].Journal of Southwest Jiaotong University,2021,56(4):785-791,838.
[8]GOH A T C,ZHANG W G,WONG K S.Deterministic and reliability analysis of basal heave stability for excavation in spatial variable soils[J].Computers and Geotechnics,2019,108:152-160.
[9]ZHANG T T,BAROTH J,DIAS D.Deterministic and probabilistic basal heave stability analysis of circular shafts against hydraulic uplift[J].Computers and Geotechnics,2022,150:104922.
[10]毛凤山,温友鹏,朱明星,等.基于深度学习和随机场的临水基坑支护结构响应分析[J].水运工程,2023(7):205-211,224. MAO Fengshan,WEN Youpeng,ZHU Mingxing,et al.Response analysis of supporting structure of foundation pit nearby water based on deep learning and random field[J].Port & Waterway Engineering,2023(7):205-211,224.
[11]孟志豪,于同生.考虑参数空间变异性的深基坑变形响应分析[J].山西交通科技,2018(5):4-6,14. MENG Zhihao,YU Tongsheng.The deformation response analysis of deep foundation pit considering the parameters spatial variability[J].Shanxi Science & Technology of Transportation,2018(5):4-6,14.
[12]阮平南,姜宁.基于信息熵的战略网络中企业关系研究[J].科学决策,2009(4):39-43. RUAN Pingnan,JIANG Ning.A study on relationship among corporations in strategic network based on the information entropy[J].Scientific Decision Marking,2009(4):39-43.
[13]薛中营.可拓学:一门本土原创学科的创建与兴起[J].广西民族大学学报(自然科学版),2016,22(3):38-41. XUE Zhongying.Extenics:the creation and rise of a local original discipline[J].Journal of Guangxi University for nationalities (Natural Science Edition),2016,22(3):38-41.
[14]张培森,施建勇.参数空间变异性对基坑周围土体变形影响分析[J].地下空间与工程学报,2008(1):111-115,137. ZHANG Peisen,SHI Jianyong.Analysis on effect of space variability of parameters on soil deformation around the deep excavation[J].Chinese Journal of Underground Space and Engineering,2008(1):111-115,137.
[15]易顺,林伟宁,陈健,等.基于随机场理论的基坑开挖地表及围护墙变形分析[J].岩石力学与工程学报,2021,40(增刊2):3389-3398. YI Shun,LIN Weining,CHEN Jian,et al.Deformation analysis of surface and retaining wall induced by braced excavation based on random field theory[J].Chinese Journal of Rock Mechanics and Engineering,2021,40(Supplement 2):3389-3398.
[16]王上上,陈富,李东贤,等.锚杆不确定性对加固边坡失稳概率的影响[J].地质科技通报,2022,41(2):282-289. WANG Shangshang,CHEN Fu,LI Dongxian,et al.Influence of anchor uncertainty on the failure probability of reinforced slope[J].Bulletin of Geological Science and Technology,2022,41(2):282-289.
[17]王杰,黄仁东,华正阳,等.基于FLAC3D的深基坑开挖对近距离建筑的安全影响研究[J].世界科技研究与发展,2016,38(2):336-340,351. WANG Jie,HUANG Rendong,HUA Zhengyang,et al.Study on influence of deep foundation pit excavation upon adjacent building safety based on FLAC3D[J].World Sci-Tech R & D,2016,38(2):336-340,351.
[18]黄帅.基于数值模拟的超深基坑降水技术及变形研究[J].地下水,2024,46(2):47-49. HUANG Shuai.Study on dewatering technology and deformation of ultra-deep foundation pit based on numerical simulation[J].Ground Water,2024,46(2):47-49.
[19]孟凯琪,王铭浩,焦力,等.考虑基坑宽度及软弱土层厚度的基坑抗隆起稳定可靠度研究[J].青岛理工大学学报,2024,45(4):35-44. MENG Kaiqi,WANG Minghao,JIAO Li,et al.Study on the basal-heave stability and reliability of foundation pit considering excavation width and thickness of soft soil layer[J].Journal of Qingdao University of Technology,2024,45(4):35-44.
[20]叶帅华,唐宁,李京榜.降雨入渗条件下框架锚杆支护边坡稳定性与变形分析[J].地基处理,2024,6(1):77-89. YE Shuaihua,TANG Ning,LI Jingbang.Stability and deformation analysis of slope supported by frame anchors under rainfall infiltration[J].Journal of Ground Improvement,2024,6(1):77-89.
[21]刘招伟,赵运臣.城市地下工程施工监测与信息反馈技术[M].北京:科学出版社,2006.

相似文献/References:

[1]汪送,王瑛,李超.BP神经网络在航空机务人员本质安全程度评价中的应用[J].中国安全生产科学技术,2010,6(6):35.
[2]段礼祥,张来斌,钱永梅.AHP—模糊综合评价法在离心泵安全评价中的应用[J].中国安全生产科学技术,2011,7(2):127.
 DUAN Li xiang,ZHANG Lai bin,QIAN Yong mei.Application of fuzzy comprehensive evaluation in safety assessme of centrifuge pumpnt[J].Journal of Safety Science and Technology,2011,7(12):127.
[3]金珠,马小平.基于核校准和SVM的煤矿安全组织管理因素分析[J].中国安全生产科学技术,2011,7(3):16.
 JIN Zhu,MA Xiao-ping.Analysis of organizational administrative factors in coal mine safety based on kernel alignment and SVM[J].Journal of Safety Science and Technology,2011,7(12):16.
[4]郭凯旋.PTA生产火灾爆炸危险性分析与评价[J].中国安全生产科学技术,2011,7(5):167.
 GUO Kai-xuan.Analysis and Assessment on Fire & Explosion Risk for PTA Production[J].Journal of Safety Science and Technology,2011,7(12):167.
[5]朱劭涌,曹雄,刘磊,等.糠醛厂生产过程安全评价[J].中国安全生产科学技术,2011,7(6):118.
 ZHU Shao-yong,CAO Xiong,LIU Lei,et al.Safety Assessment on productive process in one furfural factory[J].Journal of Safety Science and Technology,2011,7(12):118.
[6]陈杨,王为民,姜东方,等.基于故障树与灰色模糊理论的城市CNG加气站安全评价[J].中国安全生产科学技术,2011,7(4):123.
 Chen Yang,Wang Wei-min,JIANG Dong-fang,et al.Safety Assessment of the CNG station in city based on the Faulty Tree and Fuzzy-grey Theory[J].Journal of Safety Science and Technology,2011,7(12):123.
[7]王明贤,肖伟,李建峰.基于WEB的安全评价辅助系统的研究[J].中国安全生产科学技术,2011,7(9):153.
 WANG Ming-xian,XIAO Wei,LI Jian-feng.Research on Support System for Safety Assessment Based on WEB[J].Journal of Safety Science and Technology,2011,7(12):153.
[8]巫志鹏,白永忠,林景喜.新化工装置风险评价方法的研究[J].中国安全生产科学技术,2011,7(10):154.
 WU Zhi-peng,BAI Yong-zhong,LIN Jing-xi.Study on the methods of hazard risk assessment for new facilities[J].Journal of Safety Science and Technology,2011,7(12):154.
[9]李美求,周思柱,段梦兰,等.重点石化生产工程安全评价系统开发[J].中国安全生产科学技术,2011,7(10):186.
 LI Mei-qiu,ZHOU Si-zhu,DUAN Meng-lan,et al.Development ofsafety assessment?system for the Key projects of petrochemical production[J].Journal of Safety Science and Technology,2011,7(12):186.
[10]裴金勇,曾伟,李莹,等.基于DEMATELANP水电施工现场安全评价模型研究[J].中国安全生产科学技术,2012,8(7):89.
 PEI Jin yong,ZENG Wei,LI Ying,et al.Research on safety assessment model of hydroelectric construction site with DEMATEL and ANP[J].Journal of Safety Science and Technology,2012,8(12):89.

备注/Memo

备注/Memo:
收稿日期: 2025-06-29
* 基金项目: 国家自然科学基金项目(42467019)
作者简介: 荆宏亮,硕士研究生,主要研究方向为基坑施工安全。
通信作者: 李亮,博士,教授,主要研究方向为岩土工程防灾减灾。